SATISFYING the 4-hour fire rating requirement without using vermiculite

2/23/2021

2 Comments

 
There were provisions to use a fill material for hollow units to increase the fire resistance rating. In past, materials like zonolite (vermiculite) were used and a 6\" filled hollow unit would provide over 4 hours of fire resistance. Due to asbestos issues, vermiculite is no longer used. Is there a similar product that can be used?

The fill material could be a variety of material, The key is what the CMU is manufactured with. If the 6" CMU is manufactured using sand and/or limestone aggregate you cannot reach a 4 hr equivalent rating. What you fill the cores with takes on the rating as the CMU. Full lightweight CMU with cores filled will meet a 4 hr requirement. A proper blend of sand and lightweight with filled cores may meet 4 hrs. The blend will have to be verified by an independent lab. Fill material can be practically anything that is fireproof itself. Perlite, sand, expanded clay aggregate and masonry cell fill (course or fine grout) are possibilities.  

The Masonry Society has an excellent book on Fire Resistance of Masonry. Chapter 7 Section 722 covers calculated fire resistance in the IBC. I am attaching a link to the NCMA TEK that covers the same subject. 

FIRE RESISTANCE RATINGS OF CONCRETE MASONRY ASSEMBLIES - NCMA 

Thank you for contacting the MAF.  Our goal is to make sure that when masonry is designed and installed correctly the public has the best wall system available.
Be safe,
Jerry M Painter, FASTM
352-494-8955
2 Comments

Acceptable Vertical Tolerances in CMU & Brick Construction

10/17/2019

2 Comments

 
What is the acceptable vertical tolerance allowed in CMU and brick construction?
1/8\" in 10ft and 1/4\" in 20ft?
Acceptable vertical tolerances in cmu and brick are covered in TMS 402/602 Building Code Requirements and Specification for Masonry Structures. The specific location is TMS 602 Part 3 paragraph 3.3 F.2.b. It allows for a +/-1/4" in 10 lf, +/- 3/8" in 20 lf and a 1/2" maximum. Remember when checking these tolerances that the TMS 402/602 may not be the best from an atheistic standpoint. The architect can put tolerances in the project specification that are more stringent than given in the code. They may also reference documents from BIA or NCMA. Read your specifications very carefully to insure that what is stated in the specifications won't require workmanship of a higher level (more costly). Brick workmanship should always be approved using a mockup.
Remember!! There is no ASTM standard for acceptable masonry workmanship.
2 Comments

Cavity Wall Joint Reinforcement

9/26/2019

0 Comments

 
​Could an contractor use a 12\" wide truss type horizontal joint reinforcement for a cavity wall (4\" Brick + 1.5\" air gap + 8\" CMU Block)?
​The 12" truss HJR will NOT meet the requirements of TMS 402/602-16 for cavity wall construction. Your wall system will have a total width of 13.5". The actual hjr width is 10". The wire/ rod in the veneer will only have 1 1/4" coverage which is not enough. The code also requires a rod in each face of the CMU. there are several options for anchoring the veneer, If you need seismic protection then you may need the rod in the veneer. I suspect not, The hjr  with a third rod is seriously labor intensive. The bricklayers have to lay brick under the outside rod without raising it. If they do bend it up slightly they will probably not get it to lay flat on the veneer and must take undue care to get the brick above to lay to the line as well as keeping the veneer below from being displaced. The best cavity wall reinforcing and anchoring system is one that utilizes what we call a hook and eye system. It has 8" HJR for the CMU with a double eye welded to it and separate hooks that  will connect to it and lay into the veneer horizontal joint. This is the best system for production and allows for vertical and horizontal movement of the veneer. Ladder type horizontal joint reinforcing is recommended in reinforced concrete masonry.
Be safe.
Jerry Painter, FASTM
[email protected]
0 Comments

Effect of Solid Grouting on Water and Vapor Transmission?

7/3/2019

0 Comments

 
Does solid grouting of your cells in a masonry wall help to reduce the movement of water and water vapor through the wall?
The short answer is yes but not by much and it is not discussed as a way to water proof masonry walls. Integral waterproofing agents in the block, concave tooled mortar joints, exterior sealants applied to the block face, weeps and flashing and control of cracking by properly placed control joints are the prescribed methods of limiting water and vapor movement through the wall. Solid grouting can improve the structural capacity of your wall but improvement of water tightness is not an acknowledged benefit. There are just too many other more effective and less costly ways to address wall leakage. Pleaase see the attached article that addresses creating water tight masonry walls.
Additional information:
​
Keeping your Single Wythe Masonry Building Dry

https://ncma.org/resource/design-for-dry-single-wythe-walls/​​
0 Comments

    Authors:

    Picture
    Jerry Painter, FASTM
    352-378-7511
    [email protected] 

    Picture
    Don Beers, PE, GC
    561-310-9902
    [email protected]

    Categories

    All
    #5 Rebar
    Backer Rod
    Backup Wall
    Bar Hooks
    Block Strength
    Bond Beam
    Bond Breakers
    Brick
    Brick Veneer
    C129
    C90
    Cavity Wall
    Cell Size
    Cell Width
    Cmu
    Code Editions
    Code Requirements
    Codes
    Concrete Block
    Concrete Interlocking Pavers
    Concrete Pavers
    Construction Guidance
    Control Joint
    Control Joints
    Corner Attachments
    Cracking
    Crosswebs
    De-bonded Veneer
    Density
    Design Criteria
    Driveway
    Energy
    Energy Efficiency
    Energy Loss
    Envelope Leakage
    Expansion Joints
    FBC
    FBC 6th Edition
    FBC 7th Edition
    Filling Cells
    Fine Aggregate Grout
    Fire Rating
    Florida Building Code
    F''m
    Grouted Beam
    Grout Height
    Grouting
    Grouting Of Block Walls
    High Strength Masonry
    High-strength Masonry
    High Wind
    High Wind Construction
    HJR
    Horizontal Steel Spacing
    ICC 600
    ICC Code
    Infill
    In-plane
    Insulation
    Integral Waterproofing
    Interlocking Pavers
    Intermediate
    Intersecting Walls
    Job Requirements
    Jobsite
    Joint Reinforcement
    Light-weight
    Masonry
    Masonry Construction
    Masonry Details
    Masonry Insulation
    Masonry Websites
    Masonry Workmanship
    Max Bar Size
    Missile Impact
    Mortar
    Mortar Joints
    Net Area Strength
    Out-of-plane
    Perm
    Pnnl
    Psi
    Rebar
    Reinforcement
    Residential
    R Value
    Safety
    Setting Pavers
    Shear Walls
    Shrinkage
    Slip Joints
    Sound Insulation
    Sound Transmission
    Split-face Block
    STC Rating
    Sticky Stone
    Stucco
    Stucco Bonding
    Stucco Over Lath
    Table 2
    Thin Veneer
    Tie Beams
    TMS
    TMS 402/602
    Tyvek
    UL
    UL Labeling
    Vapor Barrier
    Vertical Steel
    Vertical Walls
    Videos
    Wall Bending
    Wall Design
    Wall Tolerances
    Water Intrusion
    Waterproofing
    Water Vapor
    Wind

    Archives

    May 2024
    April 2024
    March 2024
    March 2022
    February 2022
    January 2022
    October 2021
    August 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    October 2020
    September 2020
    August 2020
    July 2020
    May 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018

    RSS Feed

Masonry Resources

Clay Brick Masonry
Concrete Masonry
Mortar & Grout
Reinforcing Steel
Sustainability & LEED
Wall System Comparisons


MAF Websites

​Find out more about Masonry
​Pre-Apprentice Programs by visiting:
www.MasonryEducation.org
Picture
Masonry Association of Florida, Inc. |PO Box 24474 , Fort Lauderdale, FL 33307
Copyright  ©  2017. All Rights Reserved.
Sitemap
  • News
  • Knowledge Base
  • FloridaMasonry.com
  • CWFN Home