MAF Masonry knowledge base

Masonry Association of Florida, Inc. Florida Builds with BLOCK, BRICK & Stone.
  • News
  • Knowledge Base
  • FloridaMasonry.com
  • CWFN Home

Grouting bond beams under an existing slab

1/7/2019

0 Comments

 
About eight months ago, you helped us getting some bond beam clarifications on a project we’re doing with PCL construction (see original email below). Recently we’ve encountered another bond beam issue on this project that we’re having a difficult time overcoming. The bond beam details show it located in the last course as seen it in typical applications (see attachment). Unfortunately, all of the overhead decks are installed and placed, making the installation of the bond beam on the top course very difficult to install and grout. We proposed to lower the bond beams by one course but we’re getting resistance from the engineer. PCL asked us to reach out to you in hopes that you could help shed some light into this and ease the engineers concerns that there are no structural concerns by doing this. Is this something you could take a look into and help us out with? ​

The designer was hopefully thinking that the walls would be built first before creating this detail. As you are well aware the installation of the block is not the problem although a 3/4" space at the top would be more realistic and wouldn't effect the structural support of the wall by the very healthy 4x4x3/8 angles. If the engineer felt the need you could easily increase the number of anchors on each side from 2 to 3 to compensate for the additional moment from the wall.

But that only addresses the installation of the masonry unit itself. The next problem is the installation of the grout which cannot be squirted into a 1/2" crack at the top of the wall. A common way to grout masonry walls under an existing slab is to core a 3" or 4" hole in the slab at 4' or so along the wall and grout the wall through those holes. It does sound like the engineer would like the top course grouted to increase the lateral load resistance. Failing being able to grout the top course through the cover slab you could engage some exotic method of porting and pumping a very fine grout mixture (it wouldn't meet C-476 but would work) into the wall at a lower level.

The vertical steel is the easiest and you have probably done this many times. Just create a hand hold in the wall and slide a lapped bar up into the top course after it is laid in place.

The horz steel as detailed is virtually impossible to install as you already know. This steel can only serve two purposes: 1) to span the 6' 8" laterally between the 4x4 side plants and 2) to provide horz reinforcement for crack control. The crack control reinforcement would actually perform better in the next course down ( or 3 or 4 courses down - makes no difference). Concern about the wall spanning laterally 6' 8" could be addressed by simply reducing the steel size to a #3 bar which could be slid into a hand hole in the top course. Another solution would be to distribute your latter supporting 4x4 angles down the length of the wall rather and a single 18" long piece at 8' o/c. Say... something like a 4x4x4" lg piece at 2' o/c. Your lateral bending between the supports then becomes insignificant and your (2) #5 bars in the second course down would take care of your crack control slightly more efficiently then if they were in the top course.

Other than that you can form and pour the top course which still doesn't address how you get the concrete into it.

I am honestly surprised that the engineer of record would not immediately recognize that he had created an extremely difficult (impossible) detail to construct and be helpful in rectifying the situation. If it has not already been done I would recommend providing him with the opportunity to come up with a reasonable engineering solution to the problem. Perhaps he has not been informed of the problem?
​
Links to additional information:

CMU Wall Details: 
https://bit.ly/2GZRWhC​ 
0 Comments



Leave a Reply.

    Authors:

    Picture
    Jerry Painter, FASTM
    352-378-7511
    [email protected] 

    Picture
    Don Beers, PE, GC
    561-310-9902
    [email protected]

    Categories

    All
    #5 Rebar
    Backer Rod
    Backup Wall
    Bar Hooks
    Block Strength
    Bond Beam
    Bond Breakers
    Brick
    Brick Veneer
    C129
    C90
    Cavity Wall
    Cell Size
    Cell Width
    Cmu
    Code Editions
    Code Requirements
    Codes
    Concrete Block
    Concrete Interlocking Pavers
    Concrete Pavers
    Construction Guidance
    Control Joint
    Control Joints
    Corner Attachments
    Cracking
    Crosswebs
    De-bonded Veneer
    Density
    Design Criteria
    Driveway
    Energy
    Energy Efficiency
    Energy Loss
    Envelope Leakage
    Expansion Joints
    FBC
    FBC 6th Edition
    FBC 7th Edition
    Filling Cells
    Fine Aggregate Grout
    Fire Rating
    Florida Building Code
    F''m
    Grouted Beam
    Grout Height
    Grouting
    Grouting Of Block Walls
    High Strength Masonry
    High-strength Masonry
    High Wind
    High Wind Construction
    HJR
    Horizontal Steel Spacing
    ICC 600
    ICC Code
    Infill
    In-plane
    Insulation
    Integral Waterproofing
    Interlocking Pavers
    Intermediate
    Intersecting Walls
    Job Requirements
    Jobsite
    Joint Reinforcement
    Light-weight
    Masonry
    Masonry Construction
    Masonry Details
    Masonry Insulation
    Masonry Websites
    Masonry Workmanship
    Max Bar Size
    Missile Impact
    Mortar
    Mortar Joints
    Net Area Strength
    Out-of-plane
    Perm
    Pnnl
    Psi
    Rebar
    Reinforcement
    Residential
    R Value
    Safety
    Setting Pavers
    Shear Walls
    Shrinkage
    Slip Joints
    Sound Insulation
    Sound Transmission
    Split-face Block
    STC Rating
    Sticky Stone
    Stucco
    Stucco Bonding
    Stucco Over Lath
    Table 2
    Thin Veneer
    Tie Beams
    TMS
    TMS 402/602
    Tyvek
    UL
    UL Labeling
    Vapor Barrier
    Vertical Steel
    Vertical Walls
    Videos
    Wall Bending
    Wall Design
    Wall Tolerances
    Water Intrusion
    Waterproofing
    Water Vapor
    Wind

    Archives

    May 2024
    April 2024
    March 2024
    March 2022
    February 2022
    January 2022
    October 2021
    August 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    October 2020
    September 2020
    August 2020
    July 2020
    May 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018

    RSS Feed

Masonry Resources

Clay Brick Masonry
Concrete Masonry
Mortar & Grout
Reinforcing Steel
Sustainability & LEED
Wall System Comparisons


MAF Websites

​Find out more about Masonry
​Pre-Apprentice Programs by visiting:
www.MasonryEducation.org
Picture
Masonry Association of Florida, Inc. |PO Box 24474 , Fort Lauderdale, FL 33307
Copyright  ©  2017. All Rights Reserved.
Sitemap
  • News
  • Knowledge Base
  • FloridaMasonry.com
  • CWFN Home