MAF Masonry knowledge base

Masonry Association of Florida, Inc. Florida Builds with BLOCK, BRICK & Stone.
  • News
  • Knowledge Base
  • FloridaMasonry.com

Intermediate bond beams in grout pours more than 5’4”

12/31/2019

0 Comments

 
We are building a project with 9’ 4” walls. The walls have vertical steel in poured cells at 16” on center and a single 8”x8” bond beam one course down from the top of the wall. The top course is regular block with only every other core grouted above the vertical poured cells. We would like to pour this wall in a single 9’ 4” lift however the building official is telling us we must pour the wall in 5’ 4” lifts because of the bond beam one course down from the top.
The salient code section governing this discussion is out of TMS 402-2016 Section 3.2.1 and TMS 602-2016 Section 3.5 D – Grout lift height. A copy of these code sections is attached to this blog (I hope). Since the 2008 TMS 402/602 we have been allowed to grout up to 12’ 8” in a single lift if three conditions were met: 1) the masonry was at least 4 hours old, 2) the grout was fluid – 10-11 inches and 3) there were no intermediate bond beams to be grouted where we would need the grout to flow horizontally to fill the bond beams.

The next section of the code (3.5 D.1.b) tells us that if the first 2 conditions are met and we have intermediate bond beams we can grout to the bottom of the lowest bond beam above 5’ 4”. In this case that would be 9’ 4” subtract 16” or 8’ of height. So, by the book, we would place an 8’ lift then come back with a second pass and grout the bond beam and the course above.

The normal spacing of vertical and horizontal bond beams is 48” oc throughout the seismic regions of the country. In Florida we do not have the minimum 48”x48” seismic grid requirement and our bond beams are normally at the top of the wall. Thus, the code is written to ensure that the grout will flow at least 24” into any horizontal bond beam. In this particular case the grout need only flow 4” horizontally into the horizontal bond beam (remember the poured cells are only 16” on center).

It would be my hope that in this particular case common sense would prevail and the inspector or EOR would ignore the intermediate bond beam realizing that 1) it is virtually at the top of the wall and 2) the horizontal flow is MUCH, MUCH less than the distance that the code is set up to accommodate.
​
Failing common sense, section 3.2.1 of TMS 402-2016 provides for a solution through the use of a demo panel showing that the variance from the code does not affect the ability of the contractor to solidly grout the spaces in the wall receiving grout. The commentary to Section 3.2.1 gives additional guidance on the demo panel.
Links to additional information: 
​
TMS 602 Section 3.5D Grout Lift Height

Grout Minimum Spaces
0 Comments



Leave a Reply.

    Authors:

    Picture
    Jerry Painter, FASTM
    352-378-7511
    painterjm@gmail.com 

    Picture
    Don Beers, PE, GC
    561-310-9902
    don@floridamasonry.com

    Categories

    All
    #5 Rebar
    Backer Rod
    Bar Hooks
    Block Strength
    Bond Beam
    Bond Breakers
    Brick
    Brick Veneer
    C129
    C90
    Cavity Wall
    Cell Size
    Cell Width
    Cmu
    Code Editions
    Code Requirements
    Codes
    Concrete Block
    Concrete Interlocking Pavers
    Concrete Pavers
    Construction Guidance
    Control Joint
    Control Joints
    Corner Attachments
    Cracking
    Crosswebs
    De-bonded Veneer
    Density
    Design Criteria
    Driveway
    Energy
    Energy Efficiency
    Energy Loss
    Envelope Leakage
    Expansion Joints
    FBC
    FBC 6th Edition
    Filling Cells
    Fine Aggregate Grout
    Fire Rating
    Florida Building Code
    F''m
    Grouted Beam
    Grout Height
    Grouting
    Grouting Of Block Walls
    High Strength Masonry
    High-strength Masonry
    HJR
    Horizontal Steel Spacing
    Infill
    In-plane
    Insulation
    Integral Waterproofing
    Interlocking Pavers
    Intermediate
    Intersecting Walls
    Job Requirements
    Jobsite
    Joint Reinforcement
    Light-weight
    Masonry
    Masonry Construction
    Masonry Details
    Masonry Insulation
    Masonry Websites
    Masonry Workmanship
    Max Bar Size
    Missile Impact
    Mortar
    Mortar Joints
    Net Area Strength
    Out-of-plane
    Perm
    Pnnl
    Psi
    Rebar
    Reinforcement
    R Value
    Safety
    Setting Pavers
    Shear Walls
    Shrinkage
    Slip Joints
    Sound Insulation
    Sound Transmission
    Split-face Block
    STC Rating
    Sticky Stone
    Stucco
    Stucco Bonding
    Stucco Over Lath
    Table 2
    Thin Veneer
    Tie Beams
    TMS 402/602
    Tyvek
    UL
    UL Labeling
    Vapor Barrier
    Vertical Steel
    Vertical Walls
    Videos
    Wall Bending
    Wall Design
    Wall Tolerances
    Water Intrusion
    Waterproofing
    Water Vapor
    Wind

    Archives

    October 2020
    September 2020
    August 2020
    July 2020
    May 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018

    RSS Feed

Masonry Resources

Clay Brick Masonry
Concrete Masonry
Mortar & Grout
Reinforcing Steel
Sustainability & LEED
Wall System Comparisons


MAF Websites

​Find out more about Masonry
​Pre-Apprentice Programs by visiting:
www.MasonryEducation.org
Picture
Masonry Association of Florida, Inc. |PO Box 24474 , Fort Lauderdale, FL 33307
Copyright  ©  2017. All Rights Reserved.
Sitemap
  • News
  • Knowledge Base
  • FloridaMasonry.com